When it comes to early completion of flooring, the main hurdle you
have to come across is the long drying period of floor screeds. Owing
to the difficulty to predict the drying time accurately, it is always
essential to conduct a moisture assessment test before the application
of any final floor finish. Drying time for a traditional sand and
cement screed at 75mm is 110 days, while the drying time for a liquid
one at 55mm is only 70 days. But irrespective of the materials,
liquid or traditional cement and sand, conducting moisture testing prior
the installation of final floor finish is very important. There are
several methods such as Concrete Moisture Test (CM Test), Calcium
Carbide Test, Air Hygrometer Test and many others which are used to
measure the moisture level of screeds. If you are looking for a simple
device to carry out liquid screed moisture testing quickly, Hydro Testing meter is the most trusted and advanced one.
All about Hydro testing
With the demand of completing flooring projects as soon as possible,
the flooring experts end up cutting corners. In order to attain
accurate results, proper moisture testing procedures should be done to
avoid costly problems later. Using Hydro testing meter you can assess
the moisture content of floor screeds. It assesses the moisture content
of the screed by measuring its electrical impedance. This tiny but
effective moisture testing device can be stuck to any kind of floor
giving you floor humidity readings each and every minute of the day.
Within a moment, this device can tell you if your floor is ready to
take any covering or not. No matter whether you have opted for
traditional screeds or flowing screeds, don't forget to hire a screeding
company that is experienced and conduct moisture level testing before
the final covering. If you take the service of experienced
professionals they will take full care that the process is completed
with full perfection taking all important requirements under
consideration.
The drying time of liquid screeds are less compared to the traditional
cement and sand screeds. Unlike cement based screeds, the liquid ones
can be forced dried after 7 days of installation. In order to ensure
the quality, durability and good finishing of your floor coverings, you
must ensure that the screed is completely dried up and ready for use.